Town of Carolina Beach (NC)

Water Plant Upgrades

Tasks

Replace corroded materials and paint new piping in small water treatment plant.

Details

ACSC provided all equipment, labor and material to demolish all 6”, 8”, and 10” discharge piping header inside the building from the high service pumps to exiting the building for distribution. ACSC crews also demolished the existing filter tanks and associated piping completely. ACSC installed new ductile iron discharge piping header from high service pumps to exiting the building including all valves, bends, tee’s etc, new 10” Water Specialties flow meter in discharge header with capabilities of 4/20 milli amp signal, and new chemical injection points as needed. ACSC also provided all necessary hardware to complete piping including pipe supports, painted new header piping with color chosen by the client, cleaned up site of all debris/trash and disposed of all pipe, valves and fittings at proper location.