Moore County Public Utilities (NC)

Lift Station Replacement

Tasks

Install new lift station

Details

ACSC crews removed and replaced the existing Moore County Lift Station 3-1. ACSC mobilized to the site and installed new emergency bypass connection and set up temporary bypass pumping. ACSC removed existing lift station and associated equipment. ACSC installed new 6 ft. diameter precast wet well, 4 ft. diameter manhole, new gravity sewer line. Crews also installed a new Tencarva prepackaged pump station and associated, suction, and discharge pipe valves and fittings, as well as new electrical rack with rainshield, new electrical control equipment, and new generator. Finally, ACSC installed new gravel access drive, fence, final graded the site and placed seed and straw.

Before

After